when | what
|
---|
03/16/13 | Water infiltration rate test hole |
06/23/13 | Week 1: Excavation and footing forms |
06/29/13 | Week 2: Concrete footings and gravel |
07/07/13 | Week 3: Underslab layers and structure |
07/12/13 | Week 4: Slab poured and first walls up |
07/19/13 | Week 5: More 1st floor framing stuff |
07/26/13 | Week 6: 1st floor window and door headers, AND beams |
08/02/13 | Week 7: 1st floor sheathing and car decking |
08/10/13 | Week 8 and 9: 2nd floor framing and main beam goes up |
08/23/13 | Week 10: Sheathing complete, roof framing in progress |
09/08/13 | Week 11 and 12: Roof framing done, concrete floor grinding and finish |
09/20/13 | Week 13 and 14: Skylights, roofing, interior framing, sliding doors and wrapped |
09/28/13 | Week 15: Windows and doors installed |
10/13/13 | Week 16 and 17: Exterior insulation, batting, and trim flashing |
10/20/13 | Week 18: Plumbing rough-in, trim paint, trenches! |
11/03/13 | Week 19 and 20: More trenches, high density spray foam |
11/10/13 | Week 21: Blown-in blanket insulation, a deep hole, and siding start |
11/17/13 | Week 22: Exterior trim paint, sheetrock, siding half completed |
01/05/13 | Week 29: Moving in, ready or not, illegal or not! |