10th Ave ADU Construction Log:

whenwhat
03/16/13Water infiltration rate test hole
06/23/13Week 1: Excavation and footing forms
06/29/13Week 2: Concrete footings and gravel
07/07/13Week 3: Underslab layers and structure
07/12/13Week 4: Slab poured and first walls up
07/19/13Week 5: More 1st floor framing stuff
07/26/13Week 6: 1st floor window and door headers, AND beams
08/02/13Week 7: 1st floor sheathing and car decking
08/10/13Week 8 and 9: 2nd floor framing and main beam goes up
08/23/13Week 10: Sheathing complete, roof framing in progress
09/08/13Week 11 and 12: Roof framing done, concrete floor grinding and finish
09/20/13Week 13 and 14: Skylights, roofing, interior framing, sliding doors and wrapped
09/28/13Week 15: Windows and doors installed
10/13/13Week 16 and 17: Exterior insulation, batting, and trim flashing
10/20/13Week 18: Plumbing rough-in, trim paint, trenches!
11/03/13Week 19 and 20: More trenches, high density spray foam
11/10/13Week 21: Blown-in blanket insulation, a deep hole, and siding start
11/17/13Week 22: Exterior trim paint, sheetrock, siding half completed
01/05/13Week 29: Moving in, ready or not, illegal or not!